AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 9 DECEMBER

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We are entering a period of construction where we anticipate that there will be more HGV movements. We would like to assure you that we will work to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day
Monday

General materials  

Timber lorries

50  

24

Tuesday

General materials

Timber lorries

50

24

Wednesday

General materials

Timber lorries

35

24

Thursday

General materials

Timber lorries

35

24

Friday

General materials

Timber lorries

35

24

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.