AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 10 FEBRUARY

Please see below an update on anticipated transport movements and hauliers to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

On Thursday 13th February, between 11am – 12pm, there will be temporary traffic management on the road between Thurston Manor and the turn into Innerwick. It will consist of STOP/GO signs. We will work to minimise disruption locally and please get in touch with questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday

General materials  

Timber lorries

20  

24

Tynedale (NWH)
 Breedon
Tuesday

Rebar concrete

Timber lorries

65

24

BRC
Breedon & Aggregate Industries
Wednesday

General materials

Timber lorries

20

24

Tynedale (NWH)
Breedon
Thursday

Rebar concrete

Timber lorries

10

24

BRC
Breedon & Aggregate Industries
Friday

General materials

Timber lorries

25

24

Breedon
Tynedale (NWH)

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.