To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.
We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | Total HGV movements per day | Haulier |
| Monday | HGV Demob Timber lorries |
2 12 |
RJ McLeod |
| Tuesday | HGV Demob Concrete Timber lorries |
2 2 12 |
RJ McLeod Breedon |
| Wednesday | HGV Demob Timber lorries |
4 12 |
RJ McLeod |
| Thursday | HGV Demob Timber lorries |
2 12 |
RJ McLeod |
| Friday | HGV Demob Timber lorries |
2 12 |
RJ McLeod |
We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.
Additional component deliveries – Mon 1, blades x 3 arriving at the site at approx 2300. Tues 2, no component deliveries. Wed 3, blades x 3 arriving at the site at approx 2300. Thur 4, blades x 3 arriving at the site at approx 2300. Fri 5, no component deliveries. Sat 6, no component deliveries. Please note these deliveries are subject to change due to operational delays. Apologies for any inconvenience caused.