AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 10 MARCH

Please see below an update on anticipated transport movements and hauliers to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We have commenced work in various locations along the public road. The work will be undertaken from the corner at pinch point 5 to the Crystal Rig site entrance. Please see map here TM PP 10 March 2025 This work will include some traffic light installs at points on the road to facilitate traffic management. We will update this on a weekly basis.

We are now in a period of construction where there are more HGV movements. We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday General materials  

Timber lorries
10  

16
Geddes
Breedon
Tuesday Rebar concrete

Timber lorries
20

16
Geddes
Breedon
Wednesday Concrete

Timber lorries
15

24
Geddes
Breedon
Thursday Concrete

Timber lorries
75

24
Breedon
Skene & Aggregate Industries Geddes
Friday Concrete

Timber lorries
10

16
Breedon  

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.