To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.
We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | Total HGV movements per day | Haulier |
| Monday |
Vestas demob |
6 12 |
|
| Tuesday |
Concrete |
4 6 12 |
Breedon |
| Wednesday |
Sand |
2 6 12 |
Tyndale (NWH) |
| Thursday |
Concrete |
4 6 12 |
Breedon |
| Friday |
HGV Demob |
2 2 6 12 |
RJ McLeod NWH |
Update Thursday 13 November. Additional component deliveries, we can now confirm that the FINAL abnormal load will take place on Friday 14 November with blades x 3 arriving at the site entrance at approx 2300. There is the potential for delays from around 2000 on the southbound A1 from Haddington to the Innerwick junction. Apologies for any inconvenience caused
We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.
We will be using stop and go boards at various point along the route to site to finalise edgeworks. Additional component deliveries – we anticipate the final abnormal load to be delivered to site in the next two weeks and will issue an update on the website when the date is confirmed.
Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused.