AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 10 November

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday  

Vestas demob
Timber lorries

6 
12  
   
Tuesday   

Concrete
Vestas demob
Timber lorries

4
6
12  
Breedon  
Wednesday    

Sand
Vestas demob
Timber lorries

2
6
12  
Tyndale (NWH)  
Thursday  

Concrete
Vestas Demob
Timber lorries

4
6
12  
Breedon    
Friday

HGV Demob
Topsoil
Vestas demob
Timber lorries  

2
2
6
12
RJ McLeod
NWH    

Update Thursday 13 November. Additional component deliveries, we can now confirm that the FINAL abnormal load will take place on Friday 14 November with blades x 3 arriving at the site entrance at approx 2300. There is the potential for delays from around 2000 on the southbound A1 from Haddington to the Innerwick junction. Apologies for any inconvenience caused

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

We will be using stop and go boards at various point along the route to site to finalise edgeworks. Additional component deliveries – we anticipate the final abnormal load to be delivered to site in the next two weeks and will issue an update on the website when the date is confirmed.

Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused.