AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 12 January

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday   HGV tanker

2   Universal Waste  
Tuesday    Subsoil  

4 NWH
Wednesday   Subsoil
Tar/stone
Cabin demob

4
4
12
NWH
NWH
Portakabin  
Thursday   Subsoil
Tar/stone
 
4
4
NWH
NWH
Friday No HGV movements anticipated
 
0  

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

Additional component deliveries are now complete. Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused. Please direct any queries to Cris Thacker on 07353 962 758