AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 14 July

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text and email alerts here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday     Sand
HGV Demob
Timber lorries
2
2
12  
Tynedale (NWH)
RJ McLeod
Tuesday     Sand
HGV Demob
Timber lorries
2
2
12  
Tynedale (NWH)
RJ McLeod
  Wednesday     Sand
HGV Demob
Timber lorries
2
2
12
Tynedale (NWH)
RJ McLeod
  Thursday     Sand
HGV Demob
Timber lorries  
2
2
12
Tynedale (NWH)
RJ McLeod
Friday     Sand
HGV Demob
Timber lorries

2
2

12  

Tynedale (NWH)
RJ McLeod

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

Additional component deliveries – Mon 14, turbine blades x 3 arriving at the site at approx 2300. Tues 15, no component deliveries. Wed 16, nacelle, power train and hub arriving at site at approx 0730. Thur 17, tower sections x 3 arriving at the site at approx 2300. Fri 18, power train arriving at site at approx 0730. Sat, no component deliveries. Please note these deliveries are subject to change due to operational delays. Apologies for any inconvenience caused