To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.
We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | Total HGV movements per day | Haulier |
| Monday | HGV demob Vestas demob |
2 6 |
RJ McLeod |
| Tuesday | Concrete Vestas demob |
2 6 |
Breedon |
| Wednesday | Concrete Vestas demob |
2 6 |
Breedon |
| Thursday | HGV demob Vestas Demob |
4 6 |
RJ McLeod |
| Friday | Vestas demob |
6 |
We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.
We will be using stop and go boards at various point along the route to site to finalise edgeworks. Please note these traffic movements are subject to change due to operational delays.
Please note that Crystal Rig IV HGV construction traffic will stop from Friday 19 December through to Monday 5 January. Apologies for any inconvenience caused.