AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 15 September

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday     HGV Demob
Timber lorries
2
12
RJ McLeod
Tuesday    Timber lorries 12  
 Wednesday     HGV Demob
Timber lorries
2
12
RJ McLeod
 Thursday   Timber lorries 12  
Friday HGV Demob
Timber lorries
2
12
RJ McLeod

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

Update – Monday 15 September

Due to the high winds last week causing operational delays onsite we have had to make alterations to this weeks planned deliveries.

This weeks deliveries will now be – Mon 15, tower sections x 3 arriving at the site at approx 2300. Tues 16, blades x 3 arriving at the site at approx 2300. Wed 17, no component deliveries. Thur 18, tower sections x 3 arriving at the site at approx 2300. Fri 19, no component deliveries. Sat 20, no component deliveries. There is the potential for delays from around 8pm on the south bound A1 from Haddington to the Innerwick junction. Apologies for the late alterations and any inconvenience caused.

Should you have any questions regarding the traffic movements please do not hesitate to contact Cris Thacker on 07353 962 758  

Additional component deliveries – Mon 15, blades x 3 arriving at the site at approx 2300. Tues 16, no component deliveries. Wed 17, tower sections x 3 arriving at the site at approx 2300. Thur 18, no component deliveries. Fri 19, blades x 3 arriving at the site at approx 2300. Sat 20, no component deliveries. There is the potential for delays from around 8pm on the south bound A1 from Haddington to the Innerwick junction. Please note these deliveries are subject to change due to operational delays. Apologies for any inconvenience caused.