AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 16 DECEMBER

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We are entering a period of construction where we anticipate that there will be more HGV movements. We would like to assure you that we will work to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day
Monday General materials  

Timber lorries
60  

24
Tuesday General materials

Timber lorries
50

24
Wednesday General materials

Timber lorries
40

24
Thursday General materials

Timber lorries
50

24
Friday General materials

Timber lorries
2

24

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.