AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 18 August

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday     HGV Demob
Timber lorries
2
12
RJ McLeod
Tuesday     HGV Demob
Concrete
Timber lorries
2
2
12  
RJ McLeod
Breedon
  Wednesday     HGV Demob
Timber lorries
4
12
RJ McLeod
  Thursday     HGV Demob
Timber lorries  
2
12
RJ McLeod
Friday     HGV Demob
Timber lorries
2
12  
RJ McLeod

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

UPDATE – Monday 18 August

Over the weekend we received an update to our component deliveries for this week, they will now be – Mon 18, no component deliveries. Tues 19, tower sections x 3 arriving at the site at approx 2300. Wed 20, tower sections x 3 arriving at the site at approx 2300. Thur 21, no component deliveries. Fri 22, no component deliveries. Sat 23, no component deliveries. Apologies for the late notification and for any inconvenience caused. Please direct any queries to Cris Thacker on 07353 962 758.