AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE w/c 19 August

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

Day Description Total HGV movements per day
Monday Imported aggregates and machine delivery  

Timber lorries
12    

24  
Tuesday General materials

Timber lorries
10

24
Wednesday Imported aggregates

Timber lorries
10

24
Thursday Imported aggregates

Timber lorries
10

24
Friday Imported aggregates

Timber lorries
10

24

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.