We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | CRIV HGV Movements | NnG HGV Movements | Haulier |
| Monday | CRIV demob Vestas demob |
2 6 |
Tar – 2 | NWH |
| Tuesday | Concrete Vestas demob |
2 6 |
Tar – 2 Concrete – 2 | NWH Breedon |
| Wednesday | CRIV demob Vestas demob |
2 6 |
Topsoil – 2 Concrete – 2 | NWH Breedon |
| Thursday | Concrete Vestas demob |
2 6 |
Concrete – 2 | Breedon |
| Friday | Vestas demob |
6 |
We have had a late notification of additional topsoil and subsoil deliveries later this week. We are expecting an additional two on Wed, two on Thur and six on Fri. Apologies for the late notification
NnG are continuing the reinstatement works at the entrance to the site, these HGV movements have been added to the table above. We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.
As we continue to demobilise from the construction site, we intend to remove the average speed cameras on the public road at the end of the month.
Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused. Please direct any queries to Cris Thacker on 07353 962 758