| Day | Description | Total HGV movements per day |
| Monday | General materials Timber lorries | 8 24 |
| Tuesday | General materials Timber lorries | 4 24 |
| Wednesday | General materials Timber lorries | 4 24 |
| Thursday | General materials Timber lorries | 4 24 |
| Friday | General materials Timber lorries | 4 24 |
There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.
We expect these movements to take place between 7am and 7pm.