AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 20 JANUARY

Please see below an update on anticipated transport movements and hauliers to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We are entering a period of construction where we anticipate that there will be more HGV movements. We would like to assure you that we will work to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday General materials  

Timber lorries
50  

24
Geddes
Tynedale (NWH)
Breedon
Tuesday General materials

Timber lorries
45

24
Geddes
Tynedale (NWH)
 BRC
Wednesday General materials

Timber lorries
45

24
Geddes
Tynedale (NWH)
BRC
Thursday General materials

Timber lorries
30

24
Geddes
Breedon
Friday General materials

Timber lorries
35

24
Geddes
Breedon

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.