AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 21 APRIL

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We have commenced work in various locations along the public road. To facilitate this work, we require to fully close a section of the road between Monday 12th May and Monday 26th May. Please see the map of the closure and the proposed diversion route. We will undertake a letter drop over the next few weeks to ensure residents are aware of the closure.

Work scheduled for the week ahead can be found on this map.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday Aggregates/Concrete    

Timber lorries
0    

6
   
Tuesday Aggregates/Concrete  

 Timber lorries
30  

12
Breedon
Geddes  
Wednesday Aggregates/Concrete  

Timber lorries
25  

12  
Tynedale (NWH)
Breedon
Thursday Aggregates/Concrete  

Timber lorries
25  

12
Geddes
Breedon
Friday Concrete  

Timber lorries
20  

8
Geddes    

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.