To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.
We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | Total HGV movements per day | Haulier |
| Monday | HGV Demob |
2 12 |
RJ McLeod |
| Tuesday | Timber lorries |
12 | |
| Wednesday | HGV Demob |
2 12 |
RJ McLeod |
| Thursday | Timber lorries |
12 | |
| Friday | Timber lorries |
12 |
We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.
Update – Tuesday 23 September
Due to operational delays the
blade delivery scheduled for Tuesday 23 September has been postponed and will
now take place on Wednesday 24 September. Apologies for the late
alterations and any inconvenience caused.
Additional component deliveries – Mon 22, blades x 3 arriving at the site at approx 2300. Tues 23, blades x 3 arriving at the site at approx 2300. Wed 24, no component deliveries. Thur 25, blades x 3 arriving at the site at approx 2300. Fri 26, no component deliveries. Sat 27, no component deliveries. On delivery days there is the potential for delays from around 8pm on the south bound A1 from Haddington to the Innerwick junction. Please note these deliveries are subject to change due to operational delays. Apologies for any inconvenience caused.