AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 23 June

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text and email alerts here.

The traffic management for this week can be found here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday Aggregates    

Timber lorries
4    

12    
Geddes        
Tuesday Aggregates/Sand  

Timber lorries  

Transformer transport
14  

12  

2
Geddes
Tynedale (NWH)        



Approx 0930-1030am  
Wednesday Concrete  

Timber lorries  
2  

12  
Breedon        
Thursday Aggregates  

Timber lorries  
4  

12  
Geddes    
Friday Aggregates/Concrete  

Timber lorries  
6  

12
Geddes
Breedon  

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.