AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 25 NOVEMBER

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We are entering a period of construction where we anticipate that there will be more HGV movements. We would like to assure you that we will work to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.  

DayDescriptionTotal HGV movements per day
MondayGeneral materials  

Timber lorries
70  

24
TuesdayGeneral materials

Timber lorries
60

24
WednesdayGeneral materials

Timber lorries
20

24
ThursdayGeneral materials

Timber lorries
16

24
FridayGeneral materials

Timber lorries
8

24

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.