Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).
Please note, the section of road that has been closed will reopen at 3pm on Monday 26th May.
On Tuesday 27th May, between 1pm – 3pm there will be a delivery to site under Police escort. Traffic may move more slowly at this time.
Traffic management for the week ahead can be found here.
We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | Total HGV movements per day | Haulier |
| Monday | Aggregates Timber lorries |
8 8 |
Geddes |
| Tuesday | Aggregates Timber lorries |
0 0 |
|
| Wednesday | Aggregates Timber lorries |
8 16 |
Geddes |
| Thursday | Aggregates Concrete Timber lorries |
10 16 |
Geddes Breedon |
| Friday | Aggregates, Concrete Timber lorries |
10 16 |
Geddes Breedon |
There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.
We expect these movements to take place between 7am and 7pm.