AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 28 July

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday     Sand
HGV Demob
Type 1
Timber lorries
2
2
8
12  
Tynedale (NWH)
RJ McLeod
Geddes
Tuesday     Sand
HGV Demob
Timber lorries
2
2
12  
Tynedale (NWH)
RJ McLeod
Wednesday     Sand
HGV Demob
Type 1
Timber lorries
2
2
8
12
Tynedale (NWH)
RJ McLeod
Geddes
Thursday     Sand
HGV Demob
Timber lorries  
2
2
12
Tynedale (NWH)
 RJ McLeod
Friday     Sand
HGV Demob
Timber lorries
2
2
12  
Tynedale (NWH)
RJ McLeod

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

Additional component deliveries – there are no additional component deliveries planned for next week due to the availability of the escort services. Please note these deliveries are subject to change due to operational delays. Apologies for any inconvenience caused.