AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 29 September

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday   Timber lorries

12  
Tuesday    Timber lorries

12  
Wednesday     HGV Demob
Timber lorries

2
12
RJ McLeod
Thursday   Timber lorries

12  
Friday HGV Demob
Timber lorries  

2
12
RJ McLeod

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

Additional component deliveries – Mon 29, no component deliveries. Tues 30, tower sections x 3 arriving at the site at approx 2300. Wed 1, blades x 3 arriving at the site at approx 2300. Thur 2, no component deliveries. Fri 3, tower sections x 3 arriving at the site at approx 2300. Sat 4, no component deliveries. On delivery days there is the potential for delays from around 8pm on the south bound A1 from Haddington to the Innerwick junction. Please note these deliveries are subject to change due to operational delays. Apologies for any inconvenience caused.