Please see below an update on anticipated transport movements to and from site to facilitate the construction of Crystal Rig IV.
| Day | Description | HGV Movements |
| Monday | Import Aggregate, Fencing Materials, 2 x Excavators | 7 |
| Tuesday | General Materials Delivery of Forwarder (forestry) | 5 |
| Wednesday | Imported Aggregates 6 loads – timber haulage | 16 |
| Thursday | Imported Aggregates 10 loads – timber haulage | 20 |
| Friday | Imported Aggregates 10 loads – timber haulage | 20 |
There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.
We expect these movements to take place between 7am and 7pm.