AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 3 FEBRUARY

Please see below an update on anticipated transport movements and hauliers to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We are entering a period of construction where we anticipate that there will be more HGV movements. We would like to assure you that we will work to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday General materials  

Timber lorries
25  

24
Tynedale (NWH)
Breedon
Tuesday Rebar concrete

Timber lorries
65

 24
BRC
Breedon & Aggregate Industries
Wednesday General materials

Timber lorries
25

24
Tynedale (NWH)
Breedon
Thursday Rebar concrete

Timber lorries
65

24
BRC
Breedon & Aggregate Industries
Friday General materials

Timber lorries
20

24
Breedon
Tynedale (NWH)

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.