AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 3 MARCH

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We are now in a period of construction where there are more HGV movements. We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday General materials  

Timber lorries
10  

12
Geddes
Breedon
Tuesday Rebar concrete

Timber lorries
10

12
Geddes
Wednesday Concrete

Timber lorries
15

24
Geddes
Breedon
Thursday Concrete

Timber lorries
75

24
Breedon
Skene & Aggregate Industries Geddes
Friday Concrete

Timber lorries
10

16
Breedon  

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.