Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).
We are now in a period of construction where there are more HGV movements. We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | Total HGV movements per day | Haulier |
| Monday | General materials Timber lorries |
10 12 |
Geddes Breedon |
| Tuesday | Rebar concrete Timber lorries |
10 12 |
Geddes |
| Wednesday | Concrete Timber lorries |
15 24 |
Geddes Breedon |
| Thursday | Concrete Timber lorries |
75 24 |
Breedon Skene & Aggregate Industries Geddes |
| Friday | Concrete Timber lorries |
10 16 |
Breedon |
There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.
We expect these movements to take place between 7am and 7pm.