AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 30 June

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text and email alerts here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier
Monday Aggregates  

Timber lorries  
4  

12  
Geddes      
Tuesday Concrete  

Timber lorries
2  

12  
Breedon  
Wednesday Sand  

Timber lorries  
10  

12  
Tynedale (NWH)      
Thursday Concrete  

Timber lorries  
2  

12  
Breedon      
Friday Aggregates  

Timber lorries
4  

12  
Geddes      

We expect these movements to take place between 7am and 7pm.

Additional component deliveries – Mon 30, power train and nacelle arriving at the site at approx 0730. Tues 1, nacelle and hub arriving at site at approx 0730. Wed 2, power train and nacelle arriving at the site at approx 0730. Thur 3, nacelle and hub arriving at site at approx 0730. Fri 4, power train and hubs arriving at the site at approx 0730. Sat, no deliveries. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite. Please note these deliveries are subject to change due to operational delays. Apologies for any inconvenience caused.