AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 31 MARCH

Please see below an update on anticipated transport movements and hauliers to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

We have commenced work in various locations along the public road. Please see map. This work will include some traffic light installs at points on the road to facilitate traffic management. We will update this on a weekly basis.

We are now in a period of construction where there are more HGV movements. We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day

Description

Total HGV movements per day

Haulier

Monday

Aggregates/Concrete

 

 

Timber lorries

35

 

 

12

Geddes

Breedon

NWH

 

 

Tuesday

Aggregates/Concrete

 

Timber lorries

80

 

24

Geddes

Breedon

Skene & AI

Wednesday

Aggregates/Concrete

 

Timber lorries

25

 

24

 

Geddes

Breedon

Thursday

Aggregates/Concrete

 

Timber lorries

20

 

24

Geddes

Friday

Concrete

 

Timber lorries

5

 

16

Geddes

Breedon

 

 

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.