AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 4 NOVEMBER

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

Day Description Total HGV movements per day
Monday General materials  

Timber lorries
4  

24
Tuesday General materials

Timber lorries
4

24
Wednesday General materials

Timber lorries
16

24
Thursday General materials

Timber lorries
16

24
Friday General materials

Timber lorries
4

24

There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.

We expect these movements to take place between 7am and 7pm.