AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 8 December

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description Total HGV movements per day Haulier

Monday   Subsoil
Vestas demob
Timber lorries

8
6
12  
NWH  
Tuesday    Concrete
Vestas demob
Timber lorries

4
6
12  
Breedon  
Wednesday     Concrete
HGV demob
Vestas demob
Timber lorries

4
4
6
12  
Breedon RJ McLeod
Thursday   HGV demob
Vestas Demob
Timber lorries

4
6
12  
RJ McLeod    
Friday HGV Demob
Vestas demob
Timber lorries  

4
6
12
RJ McLeod      

We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

We will be using stop and go boards at various point along the route to site to finalise edgeworks. Additional component deliveries are now complete.

Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused.