AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 9 February

Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).

To get the most up to date information about this, please subscribe to our text alerts here and to receive combined alerts for all energy development construction in the area sign up to the East Lammermuir Community Council’s email bulletins here.

We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns. 

Day Description CRIV HGV Movements NnG HGV Movements Haulier
Monday Vestas demob   6 Tar/Spoil – 12
Materials – 4

NWH
RJM
Tuesday CRIV demob
Vestas demob
 
4
6
Tar/Spoil  – 4
Materials – 4
NWH
RJM
Wednesday Materials
Vestas demob
 
4
6
   
Thursday Materials
CRIV demob
Vestas demob  

4
4
6
   
Friday Vestas demob
 
6    

NnG are continuing the reinstatement works at the entrance to the site, these HGV movements have been added to the table above. We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite.

Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused. Please direct any queries to Cris Thacker on 07353 962 758