Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV. Movements constitutes HGV travel to site (1 movement) and return trip from site (1 movement).
Traffic management for the week ahead can be found here.
As of 16 June, we will begin transporting the turbine components to site. Sections of the turbines require to be transported under abnormal load escort by Police Scotland. This means there may be changes at short notice due to operational circumstances out with our control. We will shortly send out communications to each home in the area. To get the most up to date information about this, please subscribe to our text and email alerts here.
We would like to assure you that we are working to minimise disruption locally and we encourage you to get in touch should you have any questions or concerns.
| Day | Description | Total HGV movements per day | Haulier |
| Monday |
Aggregates Timber lorries Vestas |
8 10 6 |
Geddes Nixons |
| Tuesday |
Aggregates/Concrete Timber lorries Vestas |
52 10 8 |
Geddes Nixons |
| Wednesday |
Aggregates/Concrete Timber lorries Vestas |
20 10 9 |
Geddes DSV |
| Thursday |
Aggregates Timber lorries Vestas |
8 8 6 |
Geddes DSV Nixons |
| Friday | Aggregates/Concrete Timber lorries Vestas |
12 8 6 |
Geddes Breedon DSV Nixons |
There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.
We expect these movements to take place between 7am and 7pm.