Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV.
Main Contractor:
| Day | Description | HGV Movements |
| Monday | Import Aggregate, Fencing Materials, 2 x Excavators | 7 |
| Tuesday | General Materials Delivery of Forwarder (forestry) | 5 |
| Wednesday | Imported Aggregates | 10 |
| Thursday | Imported Aggregates | 20 |
| Friday | Imported Aggregates | 10 |
There will be other smaller deliveries with site resources, but these are the main HGV loads due onsite for our main contractor.
Looking forward
- Planned export of timber to commence w/c 5th August