AN UPDATE ON TRANSPORT MOVEMENTS
Please see below an update on anticipated transport movements to facilitate the construction of Crystal Rig IV.
Mon 22nd of July
- Cabin delivery (unit for gateman at site entrance)
- Cabin delivery (unit for compound area)
Tues 23rd July
- Cabin delivery (Portacabin delivery of site welfare)
- Cabin delivery (RJM canteen & toilet)
There will be other smaller deliveries with site resources, but these are the main heavy loads due onsite for our main contractor in the first week.
We anticipate that forestry will be the main focus of site work for this first phase of the construction. Details of forestry traffic are as follows:
Mon 22nd July
- 3 Harvesters transported to site
Ongoing – 10 days with minor road upgrades (Onsite High Road)
- 1 delivery of Excavator – dumper and tractor with vibrating roller
- 2-3 delivery trucks with road materials – (Only 15 to 20-loads of stone over the 10 days to repair onsite road)
- Planned export of timber– will not commence until 05/08